1,When the equipment arrives at the factory, it is properly kept after unloading; The whole machine of the rubber making system needs to distribute 40KW, 11KW compressor or the same flow of compressed air (with 1 cubic gas tank), steam pipe (DN25), water supply pipe (DN50) |
2,The supplier provides a list of materials before installation, and the demander prepares it according to the list |
3,After the supplier's installation engineer enters the site: open the package to check the condition of the materials and equipment, and position the equipment according to the floor plan, which takes 1 day. |
4,Equipment installation - mainly the connection of pipes, water, electricity, compressed air, steam between storage barrels, (Glue pipes on the site of the production line); 2 days to complete |
5,Power connection and debugging, completed in 1 days |
6,Stop docking the original glue pipe, which takes 1 day |
7,Enter the formula debugging glue and determine the formula, which takes 5 day. |
8,Normal use, enter the whole machine acceptance link, the above 7 items a total of 10 days |